April 18, 2007

Resident Participation

There are no Open Space resident activities scheduled at this time, walkthroughs are open to all Genesee residents and will be scheduled once management prescriptions are made.  Please look for information in monthly issues of the Genescene, Comcast cable channel 8, mail box flyers and here on this web page for upcoming events.

2007 Open Space Management Timeline

November 2006 

  • Genesee Ecosystem Management Committee review of the Open Space Managers Report to submit to the Board of Directors with attached comments / suggestions.

December 2006  

  • Genesee Foundation Board of Director review of the Open Space Managers Report with comments / suggestions from the Genesee Ecosystem Management Committee.
  • Review of Open Space volunteer opportunities.
  • Sanitation tree removal continues.

January 2007

  • Sanitation tree removal continues.
  • Request for proposals solicited from forestry professional to prepare a marking report for Open Space management activities.

February 2007

  • Tree marking complete in Dwarf Mistletoe and shaded fuel break management areas.

March 2007

  • Resident walkthrough and review of Open Space management areas scheduled.
  • Resident comments compiled and submitted to the Board of Directors for review at scheduled Board meeting.

April 2007

  • Resident walkthrough and review of Open Space management areas scheduled.
  • Draft Open Space Management Plan presented to the Board of Directors for approval.
  • Bids solicited and contractor selected for tree removal.

May 2007

  • Tree removal work begins for dwarf mistletoe management areas.

June 2007

  • Tree removal work begins for shaded fuel break management areas.
  • Open Space tree removal work in other areas continued.

July 2007

  • Open Space tree removal work continued.

August 2007

  • Open Space tree removal work continued.

September 2007

  • Open Space tree removal work continued.

October 2007

  • Open Space tree removal work continued.

November 2007

  • 2008 Open Space management timeline reviewed by the Genesee Ecosystem Management Committee and submitted to the Board of Directors.
  • 2008 Open Space Managers Report reviewed by the Genesee Ecosystem Management Committee..
  • 2007 Open Space work complete.

December 2007

  • 2008 Open Space volunteer activities reviewed by the Genesee Ecosystem Management Committee.
  • Approval / denial of the 2008 Open Space Managers Report by the Board of Directors.
  • 2007 Open Space management evaluation complete.

 