April 18, 2007
Three area has been identified (see project map),
work is almost complete.
Erosion Control Pruning Timeline
February 2007
- Letters were mailed to residents that live
adjacent to the erosion area to inform them of the upcoming work.
March 2007
- Upper culvert was re-graded and backfilled.
April 2007
- Work on the culvert that carries water under Stonecrop Way still
needs to be complete. Re-seeding of the area should occur.
May - October 2007
- All erosion work complete.
November 2007
- Evaluate erosion control Management project to identify any areas in
need of improvement.
December 2007
- Evaluate erosion control Management project to identify any areas in
need of improvement.
|